Porthole Installation Guide A:
With concealed fastening
This guide describes the installation of portholes and vision panels with concealed fastening. This version is designed for frames made of aluminium or stainless steel L-profile.
Installation diagram explained interactively
The numbers in the technical drawing correspond to the installation steps.
Click or touch a point to jump directly to the relevant step.
Tip for touch devices: Tap a point for details • press and hold to jump
Installation in seven clear steps
From the central alignment of the mounting frame to the finished glazing: the following steps guide you cleanly through the installation of Version A with concealed fastening.
Insert the mounting frame centrally
Insert the mounting frame with right-hand thread into the prepared cut-out and align it centrally. Then wedge the frame neatly in place so that it cannot slip during the subsequent installation steps.
Screw in the stud bolts evenly
Screw four stud bolts into the mounting frame using the side with the right-hand thread. The pointed side of each stud bolt has the left-hand thread. Each stud bolt is screwed in by no more than one thread pitch.
Then adjust all four stud bolts to exactly the same height using a depth gauge, for example the depth gauge of a caliper.
Clamp the glass pane centrally
Insert the glass pane centrally and loosely clamp it with three to four small wooden blocks. The blocks are secured with silicone to prevent them from slipping.
Recommended dimensions for the spacer blocks:
- Width: 10 to 15 mm
- Length: according to the leaf thickness
- Height: approximately half the clearance between glass and cut-out
Fit and screw on the glazing frame
Place the glazing frame onto the stud bolts. Then screw both frames together evenly using the supplied angled 6 mm open-end wrench.
Start with the stud bolt whose tip first makes contact with the left-hand thread of the mounting frame.
Set the gap clearance for the glazing gasket
Half the distance between the glazing frame and the glass pane is set as the gap clearance for the glazing gasket between the glass pane and the mounting frame. Suitable glazing spacer blocks are used for this purpose.
Suitable glazing spacer blocks:
- Red: 2 mm
- Green: 3 mm
- Yellow: 4 mm
- Blue: 5 mm
Insert the glazing wedge gasket on the glazing frame
Insert the supplied glazing wedge gasket between the glass pane and the glazing frame. Work evenly and make sure that the gasket sits cleanly in the intended joint.
Insert the wedge gasket on the mounting frame and remove spacer blocks
Now insert the glazing wedge gasket between the glass pane and the mounting frame. The glazing spacer blocks inserted in step 5 are removed again during this process.
Do not overtighten the screws
The screws may only be tightened until both metal rings sit cleanly against each other. The maximum torque is 1.5 Nm.
If the screws are tightened too much, the welded internal threaded bushings may tear off or indentation marks may appear on the visible surfaces.
The result
When installed correctly, the result is a cleanly framed vision panel with a centrally positioned glass pane, even glazing and concealed fastening for a particularly calm, high-quality visible surface.
Further technical information
Back to the porthole overview, to the glazing options or to the price inquiry for portholes.