Porthole Installation Guide C:
With fastening visible on both sides
This guide describes the installation of portholes and vision panels with fastening visible on both sides. This version is suitable for frames made of aluminium or stainless steel L-profile.
Installation diagram explained interactively
The numbers in the technical drawing correspond to the installation steps.
Click or touch a point to jump directly to the relevant step.
Tip for touch devices: Tap a point for details • press and hold to jump
Installation in six clear steps
From fixing the first ring to the finished glazing: the following steps guide you safely through the installation of Version C.
Fix the first ring
Position one of the two rings, the mounting frame with sleeve nuts and fitted plastic sleeves, on one side of the cut-out and temporarily fix it with adhesive tape.
Insert the glass pane centrally
Insert the glass pane centrally into the cut-out and loosely clamp it with three to four small wooden blocks. The blocks are secured with silicone to prevent them from slipping.
Recommended dimensions for the spacer blocks:
- Width: 10 to 15 mm
- Length: according to the leaf thickness
- Height: approximately half the clearance between glass and cut-out
Screw on the second ring
Insert the second ring, the glazing frame, into the plastic sleeves using the supplied raised countersunk screws and screw it to the mounting frame.
Set the gap dimension for the glazing gasket
Half the distance between the glazing frame and the glass pane is set as the gap clearance for the glazing gasket between the glass pane and the mounting frame. Suitable glazing spacer blocks are used for this purpose.
Suitable glazing spacer blocks:
- Red: 2 mm
- Green: 3 mm
- Yellow: 4 mm
- Blue: 5 mm
Insert the glazing wedge gasket on the glazing frame
Insert the supplied glazing wedge gasket between the glass pane and the glazing frame. Work evenly and make sure that the gasket sits cleanly in the intended joint.
Insert the wedge gasket on the mounting frame and remove spacer blocks
Now insert the glazing wedge gasket between the glass pane and the mounting frame. The glazing spacer blocks inserted earlier in step 4 are removed again during this process.
Do not overtighten the screws
The screws may only be tightened until both metal rings sit cleanly against each other. The maximum torque is 1.5 Nm. If the screws are tightened too much, indentation marks may appear on the visible surfaces.
The result
When installed correctly, the result is a cleanly framed vision panel with a centrally positioned glass pane, even glazing and fastening visible on both sides as a clear technical design element.
Further technical information
Back to the portholes overview, to the glazing options or to the price inquiry for portholes.